Task Name | Task Description | Start Date | Finish Date |
Project 0 | Program Administration | Tue 5/21/02 | Mon 5/15/06 |
0.1 | Attend Kick-off Meeting | Tue 5/21/02 | Fri 7/19/02 |
0.2 | Program Start-up Activities | Tue 5/21/02 | Tue 5/21/02 |
0.2.1 | Public Presentation - TBD by CEC | Tue 5/21/02 | Tue 5/21/02 |
0.2.2 | Program Software Standardization | Tue 5/21/02 | Tue 11/5/02 |
0.2.3 | Propose and Finalize the Renewables Program Advisory Committee (RPAC) | Tue 5/21/02 | Wed 3/5/03 |
0.2.4 | Document Match Funding | Tue 5/21/02 | Mon 5/15/06 |
0.2.5 | Identify and Obtain Required Permits | Tue 5/21/02 | Tue 5/21/02 |
0.2.5a | Identify Required Permits | Wed 6/5/02 | Wed 11/26/03 |
0.2.5b | Obtain Required Permits | Mon 10/13/03 | Mon 5/15/06 |
0.3 | Program Meetings | Tue 5/21/02 | Tue 5/21/02 |
0.3.1.a | First Critical Program Review Meeting (Note: Budget Assumes 2 CPR Meetings with budget split evenly) | Tue 5/28/02 | Thu 5/26/05 |
0.3.1 b | Second Critical Program Review Meeting | Tue 5/21/02 | Tue 5/21/02 |
0.3.2 | Renewable Program Advisory & Technical Advisory? Committee Meetings (Budget Assumes 12 Meetings w/Payments of $9,304 for each meeting) | Mon 4/7/03 | Tue 3/7/06 |
0.4 | Annual Technical Briefings (Budget Assumes 3 Technical Briefings w/Payments of $21,973 per Briefing) | Mon 8/19/02 | Fri 4/29/05 |
0.5 | Program Reporting | Tue 5/21/02 | Tue 5/21/02 |
0.5.1 | Monthly Program and Project Reports (Budget Assumes 36 Mo. Reports w/Payments of $50,548 per year) | Fri 6/21/02 | Mon 5/15/06 |
0.5.2 | Annual Program and Project Reports (Budget Assumes 2 Annual Reports w/Payments of $33,914 per Annual Report) | Thu 9/18/03 | Mon 2/14/05 |
0.6 | Final Program Reports | Tue 5/21/02 | Tue 5/21/02 |
0.6.1 | Final Program Report Outline | Mon 8/19/02 | Tue 3/30/04 |
0.6.2 | Draft Final Program Report | Thu 11/27/03 | Fri 2/3/06 |
0.6.3 | Final Program Report | Wed 3/8/06 | Fri 4/21/06 |
0.7 | Final Program Meeting | Thu 3/23/06 | Mon 5/1/06 |
0.8 | Project Specific Administrative Tasks | Wed 6/5/02 | Mon 4/12/04 |
Project 1.1 | Program Planning & Analysis Project - Kick-off Meeting Date: 06/27/02 | Wed 6/5/02 | Tue 1/6/04 |
1.1.1 | Review Previous Statewide/Southern California Renewable Resource Technical and Market Potential Assessments and Define The Transmission/Distribution System Mini-Grid For This Project | Wed 6/5/02 | Tue 8/13/02 |
1.1.2.a | Develop Database of Agricultural Facilities in Southern California, Targeting the Chino Basin | Wed 6/19/02 | Fri 1/17/03 |
1.1.2.b | Develop Database of Agricultural Facilities in Southern California, Targeting the Chino Basin | Wed 6/19/02 | Thu 1/16/03 |
1.1.3.a | Inventory Landfill Facilities which Serve as Host for Bioreactor Demonstration Project | Wed 6/19/02 | Thu 10/24/02 |
1.1.3.b | Inventory Landfill Facilities which Serve as Host for Bioreactor Demonstration Project | Wed 6/19/02 | Thu 10/24/02 |
1.1.4.a | Collect Information on Sewage Treatment Plants | Wed 6/19/02 | Wed 10/30/02 |
1.1.4.b | Collect Information on Sewage Treatment Plants | Wed 6/19/02 | Wed 10/30/02 |
1.1.5 | Collect information on PV system siting requirements and Identify Potential Candidate Sites for Commercial Photovoltaic Systems | Wed 8/14/02 | Mon 12/2/02 |
1.1.6 | Collect Information on Transmission/Distribution System | Fri 7/5/02 | Fri 2/14/03 |
CProjR | Critical Project Review Meeting | Wed 1/22/03 | Fri 3/7/03 |
1.1.7 | Assess Electricity Market Potential (MW's) of biogas and commercial PV within the mini-grid region | Mon 11/11/02 | Fri 8/1/03 |
1.1.8 | Develop generation profiles of the combined biogas resources and PV based upon 1) proposed program; and 2) fully realized mini-grid market potential | Wed 12/11/02 | Mon 9/15/03 |
1.1.9.a | Conduct Power Flow Analysis within Mini-Grid Target Area | Tue 10/15/02 | Fri 2/14/03 |
1.1.9.b | Conduct Power Flow Analysis within Mini-Grid Target Area | Wed 11/6/02 | Wed 9/10/03 |
1.1.10 | Prepare Prioritized List of Pilot Projects for PV and Biogas Systems | Tue 12/3/02 | Fri 9/12/03 |
1.1.11.a | Prepare Draft ReporOutline for Project 1.1 | Mon 1/20/03 | Thu 2/20/03 |
1.1.11.b | Prepare Draft Report for Project 1.1 | Mon 3/10/03 | Fri 11/7/03 |
1.1.11.c | Prepare Final Report for Project 1.1 | Thu 11/27/03 | Fri 12/26/03 |
CPR | Critical Program Review Meeting | Fri 9/12/03 | Fri 10/10/03 |
1.1.12 | Coordination w/ Renewable Program Advisory Committee (RPAC) | Wed 1/22/03 | Tue 1/6/04 |
1.1.13.a | Preparation of Measurement & Evaluation Plans | Mon 8/19/02 | Thu 9/25/03 |
1.1.13.b | Preparation of Measurement & Evaluation Plans | Fri 9/12/03 | Tue 1/6/04 |
Project 2.1 | Enhanced Landfill Gas Production Using Bioreactors Project Kick-off Meeting Held: 4/17/03 | Tue 5/21/02 | Tue 4/25/06 |
2.1.1a | Characterize MSW and Source Separated Organic Waste to Be Placed in Both Bioreactors | Mon 4/7/03 | Thu 8/21/03 |
2.1.1.b | Characterize Food or Animal Wastes to be Placed as Amendment in the Second Bioreactor | Mon 4/7/03 | Mon 4/7/03 |
2.1.2. | Identify Amendment Source Locations for the Second Bioreactor | Mon 4/7/03 | Mon 4/7/03 |
2.1.3.a | Prepare Conceptual Design for the First Bioreactor | Thu 8/7/03 | Thu 12/18/03 |
2.1.3.b | Prepare Test and Construction Plans for the First Bioreactor | Fri 12/12/03 | Fri 3/5/04 |
CProjR1 | First Critical Project Review Meeting | Tue 3/16/04 | Tue 3/30/04 |
2.1.3.c | Prepare Conceptual Design for the Second Bioreactor | Thu 2/5/04 | Thu 2/5/04 |
2.1.3.d | Prepare Test and Construction and Plans for the Second Bioreactor | Wed 4/7/04 | Wed 4/7/04 |
2.1.4.a.(1) | Construct and Operate the First Bioreactor | Fri 4/30/04 | Mon 2/28/05 |
CProjR2 | 2nd Critical Project Review Meeting | Wed 8/18/04 | Thu 9/16/04 |
2.1.4.a(2) | Construct and Operate the First Bioreactor | Fri 4/30/04 | Mon 2/28/05 |
2.1.4.a(3) | Construct and Operate the First Bioreactor | Fri 4/30/04 | Mon 2/28/05 |
2.1.4.a(4) | Construct and Operate the First Bioreactor | Fri 4/30/04 | Fri 4/29/05 |
2.1.4.a(5) | Construct and Operate the First Bioreactor | Fri 4/30/04 | Fri 4/29/05 |
2.1.4.a(6) | Construct and Operate the First Bioreactor | Mon 1/31/05 | Fri 11/25/05 |
CProjR2 | (Optional) 2nd Critical Project Review Meeting | Fri 10/28/05 | Tue 1/10/06 |
2.1.4.b(1) | Construct and Operate the Second Bioreactor | Tue 5/21/02 | Tue 5/21/02 |
2.1.4.b(2) | Construct and Operate the Second Bioreactor | Tue 5/21/02 | Tue 5/21/02 |
2.1.4.b(3) | Construct and Operate the Second Bioreactor | Tue 5/21/02 | Tue 5/21/02 |
2.1.4.b(4) | Construct and Operate the Second Bioreactor | Tue 5/21/02 | Tue 5/21/02 |
2.1.4.b(5) | Construct and Operate the Second Bioreactor | Tue 5/21/02 | Tue 5/21/02 |
2.1.4.b(6) | Construct and Operate the Second Bioreactor | Tue 5/21/02 | Tue 5/21/02 |
2.1.5.a | Prepare Final Report Outline for Project 2.1 | Mon 2/16/04 | Mon 3/15/04 |
2.1.5.b | Prepare Draft Final Report for Project 2.1 | Mon 1/31/05 | Wed 1/25/06 |
2.1.5.c | Prepare Final Report for Project 2.1 | Mon 2/27/06 | Fri 3/24/06 |
2.1.6 | Coordinate with Renewables Project Advisory Committee | Mon 4/7/03 | Tue 4/25/06 |
2.1.7.a | Evaluate Project 2.1: Draft Report | Mon 11/28/05 | Fri 3/10/06 |
2.1.7.b | Evaluate Project 2.1: Final Report | Mon 4/3/06 | Tue 4/25/06 |
Project 2.2 | Enhanced Energy Recovery through Optimization of Anaerobic Digestion and Microturbines Project Kick-off Meeting Held: 2/28/03 | Tue 1/21/03 | Mon 1/16/06 |
2.2.1 | Process Selection | Tue 1/21/03 | Wed 9/3/03 |
2.2.2 | Site Selection and Test Plan | Wed 2/12/03 | Fri 10/24/03 |
2.2.3.a | Design Microturbine and Gas Cleaning System | Wed 2/12/03 | Fri 11/21/03 |
2.2.3.b | Design Thermal Hydrolysis and Ultrasound System | Wed 2/12/03 | Fri 11/21/03 |
CProjR1 | Critical Project Review Meeting | Tue 12/9/03 | Fri 12/26/03 |
2.2.4.a(1) | Install Microturbine and Gas Cleaning System | Tue 11/25/03 | Tue 5/11/04 |
2.2.4.a(2) | Install Microturbine and Gas Cleaning System | Tue 11/25/03 | Tue 5/11/04 |
2.2.4.a(3) | Install Microturbine and Gas Cleaning System | Tue 11/25/03 | Tue 5/11/04 |
2.2.4.b | Install Thermal Hydrolysis and Ultrasound System | Fri 12/5/03 | Thu 5/20/04 |
2.2.5.a | Collect and Analyze Data for Microturbine and Gas Cleaning System & Optimized Anaerobic Digestion System (Deliver 4 reports @ $87,073 per report) | Mon 6/21/04 | Thu 8/19/04 |
2.2.5(b) | Collect and Analyze Data for Microturbine and Gas Cleaning System & Optimized Anaerobic Digestion System (Deliver 4 reports @ $87,073 per report) | Fri 8/20/04 | Fri 11/19/04 |
2.2.5(c) | Collect and Analyze Data for Microturbine and Gas Cleaning System & Optimized Anaerobic Digestion System (Deliver 4 reports @ $87,073 per report) | Fri 11/19/04 | Fri 2/18/05 |
2.2.5(d) | Collect and Analyze Data for Microturbine and Gas Cleaning System & Optimized Anaerobic Digestion System (Deliver 4 reports @ $87,073 per report) | Mon 2/21/05 | Fri 5/20/05 |
2.2.6.a | Prepare Outline for Project 2.2 | Fri 10/10/03 | Mon 12/8/03 |
2.2.6.b | Prepare Draft Report for Project 2.2 | Fri 5/21/04 | Fri 8/19/05 |
2.2.6.c | Prepare Final Report for Project 2.2 | Tue 10/18/05 | Fri 12/16/05 |
2.2.7 | Coordinate with RPAC | Tue 1/21/03 | Mon 1/16/06 |
2.2.8.a | Evaluate Project 2.2: Draft Report | Wed 8/24/05 | Tue 11/22/05 |
2.2.8.b | Evaluate Project 2.2: Final Report | Mon 12/12/05 | Fri 12/30/05 |
Project 3.1 | Dairy Waste to Energy Project - Kick-off Meeting Held: 2/28/03 | Wed 2/5/03 | Thu 5/11/06 |
3.1.1.(a).3 | Assess, Evaluate, and Select Animal Waste to Energy Technology | Wed 2/5/03 | Mon 11/17/03 |
3.1.1.(a).1 | Assess, Evaluate, and Select Animal Waste to Energy Technology | Mon 3/17/03 | Thu 6/26/03 |
3.1.1.(a).2 | Assess, Evaluate, and Select Animal Waste to Energy Technology | Wed 2/5/03 | Fri 10/24/03 |
3.1.1.b | Assess, Evaluate, and Select Animal Waste to Energy Technology | Wed 2/5/03 | Fri 1/16/04 |
3.1.2 | Site Selection | Wed 2/5/03 | Fri 12/19/03 |
CProjR1 | Critical Project Review Meeting | Wed 12/31/03 | Fri 2/6/04 |
3.1.3.a | Develop Bench scale and other test plans and protocols | Mon 3/17/03 | Tue 9/9/03 |
3.1.3.b | Conduct bench scale and other testing activities | Mon 7/14/03 | Thu 12/4/03 |
3.1.3.c | Prepare Pilot Plant Final Design & Dairy Waste to Energy Project Test Plan | Fri 11/21/03 | Thu 4/8/04 |
CProjR2 | (Optional) 2nd Critical Project Review Meeting | Fri 4/23/04 | Thu 5/13/04 |
3.1.4(a)1 | Construct Pilot Plant(s) | Fri 5/14/04 | Wed 11/10/04 |
3.1.4(a)2 | Construct Pilot Plant(s) | Fri 5/14/04 | Mon 1/10/05 |
3.1.4(a)3 | Construct Pilot Plant(s) | Thu 8/12/04 | Fri 4/8/05 |
3.1.4(b) | Construct Pilot Plant(s) (6 months @ $50,000 per month) | Mon 2/28/05 | Fri 8/26/05 |
3.1.4(c) | Construct Pilot Plant(s) | Mon 2/28/05 | Fri 5/27/05 |
3.1.5 | Operate and Test Pilot Plant(s) (Deliver 8 reports @ $73,420 per report) | Tue 7/13/04 | Mon 9/12/05 |
3.1.6.a | Conduct Economic and Environmental Assessment | Wed 7/13/05 | Mon 12/12/05 |
3.1.6.b | Conduct Economic and Environmental Assessment | Thu 1/12/06 | Fri 2/10/06 |
3.1.7.a | Prepare Final Report Outline for Project 3.1 | Mon 12/1/03 | Fri 12/19/03 |
3.1.7.b | Prepare Draft Report for Project 3.1 | Thu 11/10/05 | Wed 1/11/06 |
3.1.7.c | Prepare Final Report for Project 3.1 | Mon 2/13/06 | Fri 3/10/06 |
3.1.8 | Coordinate with Renewables Project Advisory Committee | Wed 2/5/03 | Thu 5/11/06 |
3.1.9.a | Evaluate Project 3.1: Draft Evaluation Report | Fri 10/14/05 | Fri 2/24/06 |
3.1.9.b | Evaluate Project 3.1: Final Evaluation Report | Tue 3/28/06 | Wed 4/26/06 |
Project 3.2 | Building Integrated PV Testing and Evaluation Project | Tue 5/21/02 | Tue 11/29/05 |
3.2.1 | Building Integrated PV Testing and Evaluation Test Plan | Thu 6/20/02 | Thu 12/19/02 |
3.2.2 | Comprehensive PV System Comparison | Fri 7/5/02 | Fri 4/1/05 |
3.2.2.a | Large Systems Testing | Tue 5/21/02 | Tue 5/21/02 |
3.2.2.a(1 | 1) System site selection, permitting & Acquisition (Commonwealth match funds estimated at @ $190,000) | Fri 7/5/02 | Fri 8/29/03 |
3.2.2.a(2 | 2) Data acquisition System (DAS) letter of Notification | Fri 7/5/02 | Thu 5/15/03 |
3.2.2.a(3 | 3) Initial Characterization Report for First System | Fri 7/5/02 | Thu 10/30/03 |
3.2.2.a(4 | 4) Initial Characterization Report for Second System | Fri 7/5/02 | Thu 10/30/03 |
3.2.2.a(5 | 5) Initial Characterization Report for Third System | Fri 7/5/02 | Thu 10/30/03 |
CProjR | Critical Project Review Meeting - Proposed 03/01/04 | Mon 12/15/03 | Tue 1/13/04 |
3.2.2.a(6 | 6) 6-Month Exposure and Operation Report | Tue 7/15/03 | Wed 6/30/04 |
3.2.2.a(7 | 7) Interim Report on Large Systems Progress | Tue 7/15/03 | Fri 2/27/04 |
3.2.2.a(8 | 8) 12-Month Exposure and Operation Report | Thu 7/1/04 | Thu 12/30/04 |
3.2.2.a(9 | 9) Consumer Confidence Guidelines for Large systems | Thu 7/1/04 | Fri 4/1/05 |
3.2.2.b | Small Systems Testing | Mon 8/5/02 | Thu 6/30/05 |
3.2.2.b(1 | 1) System site selection,permitting & Acqusition | Mon 8/5/02 | Fri 11/14/03 |
3.2.2.b(2 | 2) Data acquisition System (DAS) letter of Notification | Mon 8/5/02 | Wed 12/31/03 |
3.2.2.b(3 | 3) Initial Characterization Report for First System | Mon 8/5/02 | Wed 1/28/04 |
3.2.2.b(4 | 4) Initial Characterization Report for Second System | Mon 8/5/02 | Wed 1/28/04 |
3.2.2.b(5 | 5) Initial Characterization Report for Third System | Mon 8/5/02 | Wed 1/28/04 |
CProjR | Critical Project Review Meeting | Fri 2/13/04 | Fri 3/12/04 |
3.2.2.b(6 | 6) 6-Month Exposure and Operation Report | Thu 1/29/04 | Tue 9/28/04 |
3.2.2.b(7 | 7) Interim Report on Small Systems Progress | Thu 1/29/04 | Fri 5/28/04 |
3.2.2.b(8 | 8) 12-Month Exposure and Operation Report | Wed 9/29/04 | Wed 3/30/05 |
3.2.2.b(9 | 9) Consumer Confidence Guidelines for Small systems | Wed 9/29/04 | Thu 6/30/05 |
3.2.3 | Technology Transfer | Fri 7/5/02 | Wed 3/31/04 |
3.2.3.a | 1) Initial Web Page Design | Fri 7/5/02 | Thu 10/30/03 |
3.2.3.b | 2) Web Page updates for all Systems w/ links | Thu 10/23/03 | Fri 1/28/05 |
3.2.3.c | 3) Technical Papers and Presentations | Mon 3/31/03 | Wed 3/31/04 |
3.2.3.d | 4) Four 3-day Workshops | Fri 10/31/03 | Fri 10/29/04 |
3.2.4 | Final Report for Project 3.2 | Tue 3/2/04 | Fri 7/1/05 |
3.2.5 | Coordinate with Renewables Project Advisory Committee | Fri 7/5/02 | Tue 11/29/05 |
3.2.6.a | Evaluate Project #3.2: Draft Evaluation Report | Mon 5/3/04 | Wed 8/31/05 |
3.2.6.b | Evaluate Project #3.2: Final Evaluation Report | Fri 9/30/05 | Fri 10/28/05 |
Project 3.3 | Building Integrated PV on Public Facilities Project | Tue 5/21/02 | Tue 3/7/06 |
3.3.1.a | Compile Database of Public Sector Clients | Thu 6/20/02 | Fri 11/1/02 |
3.3.1.b | Compile Database of BI-PV Equipment Vendors and Service Providers | Thu 6/20/02 | Fri 11/1/02 |
3.3.2 | Develop Evaluation Tools | Mon 8/19/02 | Thu 9/11/03 |
3.3.3 | Establish BI-PV Public Sector Loan Program (Deleted per CEC request) | Tue 5/21/02 | Tue 5/21/02 |
3.3.4.a | Select Demonstration Project Sites | Mon 11/11/02 | Mon 10/27/03 |
CProjR | Critical Project Review Meeting | Fri 10/17/03 | Tue 11/11/03 |
3.3.4.b | Finance and Construct BI-PV Systems | Tue 11/11/03 | Thu 2/10/05 |
3.3.4.b.1(1) | System No. 1: Design/ financing/permitting | Tue 11/11/03 | Mon 2/9/04 |
3.3.4.b.1(2) | System No. 1: Design/ financing/permitting | Thu 12/11/03 | Fri 4/9/04 |
3.3.4.b.1(3) | System No. 1: System Installation/performance verification | Thu 12/11/03 | Fri 4/9/04 |
3.3.4.b.2(1) | System No. 2:Design/ financing/permitting | Tue 11/11/03 | Mon 2/9/04 |
3.3.4.b.2(2) | System No. 2: System Installation/performance verification | Mon 1/12/04 | Fri 5/7/04 |
3.3.4.b.3(3) | System No. 3: Design/ financing/permitting | Mon 2/9/04 | Fri 5/7/04 |
3.3.4.b.3 | System No. 3: System Installation/performance verification | Fri 4/9/04 | Fri 8/6/04 |
3.3.4.b.4 | System No. 4: Design/ financing/permitting | Mon 2/9/04 | Fri 5/7/04 |
3.3.4.b.4 | System No. 4: System Installation/performance verification | Fri 4/9/04 | Fri 8/6/04 |
3.3.4.c | PV System Monitoring | Mon 1/12/04 | Fri 10/7/05 |
3.3.5 | Prepare Final Report for Project 3.3 | Mon 4/11/05 | Fri 1/6/06 |
3.3.6 | Coordinate with Renewables Project Advisory Committee | Thu 6/20/02 | Tue 3/7/06 |
3.3.7.a | Evaluate Project #3.3: Draft Evaluation Report | Mon 7/11/05 | Wed 12/7/05 |
3.3.7.b | Evaluate Project #3.3: Final Evaluation Report | Mon 1/9/06 | Fri 2/3/06 |