PIER Commonwealth Mini-Grid



Microsoft Project Image

Project Start:
Project Finish:
Tue 5/21/02
Mon 5/15/06


Task_Export_Table


Task Name
Task DescriptionStart DateFinish Date
Project 0
Program AdministrationTue 5/21/02Mon 5/15/06
0.1
Attend Kick-off MeetingTue 5/21/02Fri 7/19/02
0.2
Program Start-up ActivitiesTue 5/21/02Tue 5/21/02
0.2.1
Public Presentation - TBD by CECTue 5/21/02Tue 5/21/02
0.2.2
Program Software StandardizationTue 5/21/02Tue 11/5/02
0.2.3
Propose and Finalize the Renewables Program Advisory Committee (RPAC)Tue 5/21/02Wed 3/5/03
0.2.4
Document Match FundingTue 5/21/02Mon 5/15/06
0.2.5
Identify and Obtain Required PermitsTue 5/21/02Tue 5/21/02
0.2.5a
Identify Required PermitsWed 6/5/02Wed 11/26/03
0.2.5b
Obtain Required PermitsMon 10/13/03Mon 5/15/06
0.3
Program MeetingsTue 5/21/02Tue 5/21/02
0.3.1.a
First Critical Program Review Meeting (Note: Budget Assumes 2 CPR Meetings with budget split evenly)Tue 5/28/02Thu 5/26/05
0.3.1 b
Second Critical Program Review MeetingTue 5/21/02Tue 5/21/02
0.3.2
Renewable Program Advisory & Technical Advisory? Committee Meetings (Budget Assumes 12 Meetings w/Payments of $9,304 for each meeting)Mon 4/7/03Tue 3/7/06
0.4
Annual Technical Briefings (Budget Assumes 3 Technical Briefings w/Payments of $21,973 per Briefing)Mon 8/19/02Fri 4/29/05
0.5
Program ReportingTue 5/21/02Tue 5/21/02
0.5.1
Monthly Program and Project Reports (Budget Assumes 36 Mo. Reports w/Payments of $50,548 per year)Fri 6/21/02Mon 5/15/06
0.5.2
Annual Program and Project Reports (Budget Assumes 2 Annual Reports w/Payments of $33,914 per Annual Report) Thu 9/18/03Mon 2/14/05
0.6
Final Program Reports Tue 5/21/02Tue 5/21/02
0.6.1
Final Program Report OutlineMon 8/19/02Tue 3/30/04
0.6.2
Draft Final Program Report Thu 11/27/03Fri 2/3/06
0.6.3
Final Program ReportWed 3/8/06Fri 4/21/06
0.7
Final Program MeetingThu 3/23/06Mon 5/1/06
0.8
Project Specific Administrative TasksWed 6/5/02Mon 4/12/04
Project 1.1
Program Planning & Analysis Project - Kick-off Meeting Date: 06/27/02Wed 6/5/02Tue 1/6/04
1.1.1
Review Previous Statewide/Southern California Renewable Resource Technical and Market Potential Assessments and Define The Transmission/Distribution System Mini-Grid For This ProjectWed 6/5/02Tue 8/13/02
1.1.2.a
Develop Database of Agricultural Facilities in Southern California, Targeting the Chino Basin Wed 6/19/02Fri 1/17/03
1.1.2.b
Develop Database of Agricultural Facilities in Southern California, Targeting the Chino Basin Wed 6/19/02Thu 1/16/03
1.1.3.a
Inventory Landfill Facilities which Serve as Host for Bioreactor Demonstration ProjectWed 6/19/02Thu 10/24/02
1.1.3.b
Inventory Landfill Facilities which Serve as Host for Bioreactor Demonstration ProjectWed 6/19/02Thu 10/24/02
1.1.4.a
Collect Information on Sewage Treatment Plants Wed 6/19/02Wed 10/30/02
1.1.4.b
Collect Information on Sewage Treatment Plants Wed 6/19/02Wed 10/30/02
1.1.5
Collect information on PV system siting requirements and Identify Potential Candidate Sites for Commercial Photovoltaic Systems Wed 8/14/02Mon 12/2/02
1.1.6
Collect Information on Transmission/Distribution System Fri 7/5/02Fri 2/14/03
CProjR
Critical Project Review MeetingWed 1/22/03Fri 3/7/03
1.1.7
Assess Electricity Market Potential (MW's) of biogas and commercial PV within the mini-grid region Mon 11/11/02Fri 8/1/03
1.1.8
Develop generation profiles of the combined biogas resources and PV based upon 1) proposed program; and 2) fully realized mini-grid market potential Wed 12/11/02Mon 9/15/03
1.1.9.a
Conduct Power Flow Analysis within Mini-Grid Target AreaTue 10/15/02Fri 2/14/03
1.1.9.b
Conduct Power Flow Analysis within Mini-Grid Target AreaWed 11/6/02Wed 9/10/03
1.1.10
Prepare Prioritized List of Pilot Projects for PV and Biogas Systems Tue 12/3/02Fri 9/12/03
1.1.11.a
Prepare Draft ReporOutline for Project 1.1Mon 1/20/03Thu 2/20/03
1.1.11.b
Prepare Draft Report for Project 1.1Mon 3/10/03Fri 11/7/03
1.1.11.c
Prepare Final Report for Project 1.1Thu 11/27/03Fri 12/26/03
CPR
Critical Program Review MeetingFri 9/12/03Fri 10/10/03
1.1.12
Coordination w/ Renewable Program Advisory Committee (RPAC)Wed 1/22/03Tue 1/6/04
1.1.13.a
Preparation of Measurement & Evaluation PlansMon 8/19/02Thu 9/25/03
1.1.13.b
Preparation of Measurement & Evaluation Plans Fri 9/12/03Tue 1/6/04
Project 2.1
Enhanced Landfill Gas Production Using Bioreactors Project Kick-off Meeting Held: 4/17/03Tue 5/21/02Tue 4/25/06
2.1.1a
Characterize MSW and Source Separated Organic Waste to Be Placed in Both BioreactorsMon 4/7/03Thu 8/21/03
2.1.1.b
Characterize Food or Animal Wastes to be Placed as Amendment in the Second BioreactorMon 4/7/03Mon 4/7/03
2.1.2.
Identify Amendment Source Locations for the Second BioreactorMon 4/7/03Mon 4/7/03
2.1.3.a
Prepare Conceptual Design for the First Bioreactor Thu 8/7/03Thu 12/18/03
2.1.3.b
Prepare Test and Construction Plans for the First Bioreactor Fri 12/12/03Fri 3/5/04
CProjR1
First Critical Project Review MeetingTue 3/16/04Tue 3/30/04
2.1.3.c
Prepare Conceptual Design for the Second Bioreactor Thu 2/5/04Thu 2/5/04
2.1.3.d
Prepare Test and Construction and Plans for the Second Bioreactor Wed 4/7/04Wed 4/7/04
2.1.4.a.(1)
Construct and Operate the First Bioreactor Fri 4/30/04Mon 2/28/05
CProjR2
2nd Critical Project Review MeetingWed 8/18/04Thu 9/16/04
2.1.4.a(2)
Construct and Operate the First Bioreactor Fri 4/30/04Mon 2/28/05
2.1.4.a(3)
Construct and Operate the First Bioreactor Fri 4/30/04Mon 2/28/05
2.1.4.a(4)
Construct and Operate the First Bioreactor Fri 4/30/04Fri 4/29/05
2.1.4.a(5)
Construct and Operate the First Bioreactor Fri 4/30/04Fri 4/29/05
2.1.4.a(6)
Construct and Operate the First Bioreactor Mon 1/31/05Fri 11/25/05
CProjR2
(Optional) 2nd Critical Project Review MeetingFri 10/28/05Tue 1/10/06
2.1.4.b(1)
Construct and Operate the Second Bioreactor Tue 5/21/02Tue 5/21/02
2.1.4.b(2)
Construct and Operate the Second Bioreactor Tue 5/21/02Tue 5/21/02
2.1.4.b(3)
Construct and Operate the Second Bioreactor Tue 5/21/02Tue 5/21/02
2.1.4.b(4)
Construct and Operate the Second Bioreactor Tue 5/21/02Tue 5/21/02
2.1.4.b(5)
Construct and Operate the Second Bioreactor Tue 5/21/02Tue 5/21/02
2.1.4.b(6)
Construct and Operate the Second Bioreactor Tue 5/21/02Tue 5/21/02
2.1.5.a
Prepare Final Report Outline for Project 2.1 Mon 2/16/04Mon 3/15/04
2.1.5.b
Prepare Draft Final Report for Project 2.1 Mon 1/31/05Wed 1/25/06
2.1.5.c
Prepare Final Report for Project 2.1 Mon 2/27/06Fri 3/24/06
2.1.6
Coordinate with Renewables Project Advisory CommitteeMon 4/7/03Tue 4/25/06
2.1.7.a
Evaluate Project 2.1: Draft ReportMon 11/28/05Fri 3/10/06
2.1.7.b
Evaluate Project 2.1: Final ReportMon 4/3/06Tue 4/25/06
Project 2.2
Enhanced Energy Recovery through Optimization of Anaerobic Digestion and Microturbines Project Kick-off Meeting Held: 2/28/03Tue 1/21/03Mon 1/16/06
2.2.1
Process SelectionTue 1/21/03Wed 9/3/03
2.2.2
Site Selection and Test Plan Wed 2/12/03Fri 10/24/03
2.2.3.a
Design Microturbine and Gas Cleaning SystemWed 2/12/03Fri 11/21/03
2.2.3.b
Design Thermal Hydrolysis and Ultrasound System Wed 2/12/03Fri 11/21/03
CProjR1
Critical Project Review MeetingTue 12/9/03Fri 12/26/03
2.2.4.a(1)
Install Microturbine and Gas Cleaning System Tue 11/25/03Tue 5/11/04
2.2.4.a(2)
Install Microturbine and Gas Cleaning System Tue 11/25/03Tue 5/11/04
2.2.4.a(3)
Install Microturbine and Gas Cleaning System Tue 11/25/03Tue 5/11/04
2.2.4.b
Install Thermal Hydrolysis and Ultrasound System Fri 12/5/03Thu 5/20/04
2.2.5.a
Collect and Analyze Data for Microturbine and Gas Cleaning System & Optimized Anaerobic Digestion System (Deliver 4 reports @ $87,073 per report)Mon 6/21/04Thu 8/19/04
2.2.5(b)
Collect and Analyze Data for Microturbine and Gas Cleaning System & Optimized Anaerobic Digestion System (Deliver 4 reports @ $87,073 per report)Fri 8/20/04Fri 11/19/04
2.2.5(c)
Collect and Analyze Data for Microturbine and Gas Cleaning System & Optimized Anaerobic Digestion System (Deliver 4 reports @ $87,073 per report)Fri 11/19/04Fri 2/18/05
2.2.5(d)
Collect and Analyze Data for Microturbine and Gas Cleaning System & Optimized Anaerobic Digestion System (Deliver 4 reports @ $87,073 per report)Mon 2/21/05Fri 5/20/05
2.2.6.a
Prepare Outline for Project 2.2Fri 10/10/03Mon 12/8/03
2.2.6.b
Prepare Draft Report for Project 2.2Fri 5/21/04Fri 8/19/05
2.2.6.c
Prepare Final Report for Project 2.2Tue 10/18/05Fri 12/16/05
2.2.7
Coordinate with RPACTue 1/21/03Mon 1/16/06
2.2.8.a
Evaluate Project 2.2: Draft ReportWed 8/24/05Tue 11/22/05
2.2.8.b
Evaluate Project 2.2: Final ReportMon 12/12/05Fri 12/30/05
Project 3.1
Dairy Waste to Energy Project - Kick-off Meeting Held: 2/28/03Wed 2/5/03Thu 5/11/06
3.1.1.(a).3
Assess, Evaluate, and Select Animal Waste to Energy TechnologyWed 2/5/03Mon 11/17/03
3.1.1.(a).1
Assess, Evaluate, and Select Animal Waste to Energy TechnologyMon 3/17/03Thu 6/26/03
3.1.1.(a).2
Assess, Evaluate, and Select Animal Waste to Energy TechnologyWed 2/5/03Fri 10/24/03
3.1.1.b
Assess, Evaluate, and Select Animal Waste to Energy TechnologyWed 2/5/03Fri 1/16/04
3.1.2
Site Selection Wed 2/5/03Fri 12/19/03
CProjR1
Critical Project Review MeetingWed 12/31/03Fri 2/6/04
3.1.3.a
Develop Bench scale and other test plans and protocolsMon 3/17/03Tue 9/9/03
3.1.3.b
Conduct bench scale and other testing activitiesMon 7/14/03Thu 12/4/03
3.1.3.c
Prepare Pilot Plant Final Design & Dairy Waste to Energy Project Test Plan Fri 11/21/03Thu 4/8/04
CProjR2
(Optional) 2nd Critical Project Review MeetingFri 4/23/04Thu 5/13/04
3.1.4(a)1
Construct Pilot Plant(s) Fri 5/14/04Wed 11/10/04
3.1.4(a)2
Construct Pilot Plant(s) Fri 5/14/04Mon 1/10/05
3.1.4(a)3
Construct Pilot Plant(s) Thu 8/12/04Fri 4/8/05
3.1.4(b)
Construct Pilot Plant(s) (6 months @ $50,000 per month) Mon 2/28/05Fri 8/26/05
3.1.4(c)
Construct Pilot Plant(s) Mon 2/28/05Fri 5/27/05
3.1.5
Operate and Test Pilot Plant(s) (Deliver 8 reports @ $73,420 per report)Tue 7/13/04Mon 9/12/05
3.1.6.a
Conduct Economic and Environmental AssessmentWed 7/13/05Mon 12/12/05
3.1.6.b
Conduct Economic and Environmental AssessmentThu 1/12/06Fri 2/10/06
3.1.7.a
Prepare Final Report Outline for Project 3.1Mon 12/1/03Fri 12/19/03
3.1.7.b
Prepare Draft Report for Project 3.1Thu 11/10/05Wed 1/11/06
3.1.7.c
Prepare Final Report for Project 3.1Mon 2/13/06Fri 3/10/06
3.1.8
Coordinate with Renewables Project Advisory CommitteeWed 2/5/03Thu 5/11/06
3.1.9.a
Evaluate Project 3.1: Draft Evaluation ReportFri 10/14/05Fri 2/24/06
3.1.9.b
Evaluate Project 3.1: Final Evaluation ReportTue 3/28/06Wed 4/26/06
Project 3.2
Building Integrated PV Testing and Evaluation ProjectTue 5/21/02Tue 11/29/05
3.2.1
Building Integrated PV Testing and Evaluation Test Plan Thu 6/20/02Thu 12/19/02
3.2.2
Comprehensive PV System Comparison Fri 7/5/02Fri 4/1/05
3.2.2.a
Large Systems TestingTue 5/21/02Tue 5/21/02
3.2.2.a(1
1) System site selection, permitting & Acquisition (Commonwealth match funds estimated at @ $190,000)Fri 7/5/02Fri 8/29/03
3.2.2.a(2
2) Data acquisition System (DAS) letter of NotificationFri 7/5/02Thu 5/15/03
3.2.2.a(3
3) Initial Characterization Report for First System Fri 7/5/02Thu 10/30/03
3.2.2.a(4
4) Initial Characterization Report for Second System Fri 7/5/02Thu 10/30/03
3.2.2.a(5
5) Initial Characterization Report for Third System Fri 7/5/02Thu 10/30/03
CProjR
Critical Project Review Meeting - Proposed 03/01/04Mon 12/15/03Tue 1/13/04
3.2.2.a(6
6) 6-Month Exposure and Operation Report Tue 7/15/03Wed 6/30/04
3.2.2.a(7
7) Interim Report on Large Systems ProgressTue 7/15/03Fri 2/27/04
3.2.2.a(8
8) 12-Month Exposure and Operation Report Thu 7/1/04Thu 12/30/04
3.2.2.a(9
9) Consumer Confidence Guidelines for Large systems Thu 7/1/04Fri 4/1/05
3.2.2.b
Small Systems TestingMon 8/5/02Thu 6/30/05
3.2.2.b(1
1) System site selection,permitting & AcqusitionMon 8/5/02Fri 11/14/03
3.2.2.b(2
2) Data acquisition System (DAS) letter of NotificationMon 8/5/02Wed 12/31/03
3.2.2.b(3
3) Initial Characterization Report for First System Mon 8/5/02Wed 1/28/04
3.2.2.b(4
4) Initial Characterization Report for Second System Mon 8/5/02Wed 1/28/04
3.2.2.b(5
5) Initial Characterization Report for Third System Mon 8/5/02Wed 1/28/04
CProjR
Critical Project Review MeetingFri 2/13/04Fri 3/12/04
3.2.2.b(6
6) 6-Month Exposure and Operation Report Thu 1/29/04Tue 9/28/04
3.2.2.b(7
7) Interim Report on Small Systems ProgressThu 1/29/04Fri 5/28/04
3.2.2.b(8
8) 12-Month Exposure and Operation Report Wed 9/29/04Wed 3/30/05
3.2.2.b(9
9) Consumer Confidence Guidelines for Small systems Wed 9/29/04Thu 6/30/05
3.2.3
Technology TransferFri 7/5/02Wed 3/31/04
3.2.3.a
1) Initial Web Page DesignFri 7/5/02Thu 10/30/03
3.2.3.b
2) Web Page updates for all Systems w/ linksThu 10/23/03Fri 1/28/05
3.2.3.c
3) Technical Papers and Presentations Mon 3/31/03Wed 3/31/04
3.2.3.d
4) Four 3-day WorkshopsFri 10/31/03Fri 10/29/04
3.2.4
Final Report for Project 3.2Tue 3/2/04Fri 7/1/05
3.2.5
Coordinate with Renewables Project Advisory CommitteeFri 7/5/02Tue 11/29/05
3.2.6.a
Evaluate Project #3.2: Draft Evaluation ReportMon 5/3/04Wed 8/31/05
3.2.6.b
Evaluate Project #3.2: Final Evaluation ReportFri 9/30/05Fri 10/28/05
Project 3.3
Building Integrated PV on Public Facilities ProjectTue 5/21/02Tue 3/7/06
3.3.1.a
Compile Database of Public Sector ClientsThu 6/20/02Fri 11/1/02
3.3.1.b
Compile Database of BI-PV Equipment Vendors and Service ProvidersThu 6/20/02Fri 11/1/02
3.3.2
Develop Evaluation ToolsMon 8/19/02Thu 9/11/03
3.3.3
Establish BI-PV Public Sector Loan Program (Deleted per CEC request)Tue 5/21/02Tue 5/21/02
3.3.4.a
Select Demonstration Project Sites Mon 11/11/02Mon 10/27/03
CProjR
Critical Project Review MeetingFri 10/17/03Tue 11/11/03
3.3.4.b
Finance and Construct BI-PV SystemsTue 11/11/03Thu 2/10/05
3.3.4.b.1(1)
System No. 1: Design/ financing/permittingTue 11/11/03Mon 2/9/04
3.3.4.b.1(2)
System No. 1: Design/ financing/permittingThu 12/11/03Fri 4/9/04
3.3.4.b.1(3)
System No. 1: System Installation/performance verificationThu 12/11/03Fri 4/9/04
3.3.4.b.2(1)
System No. 2:Design/ financing/permittingTue 11/11/03Mon 2/9/04
3.3.4.b.2(2)
System No. 2: System Installation/performance verificationMon 1/12/04Fri 5/7/04
3.3.4.b.3(3)
System No. 3: Design/ financing/permittingMon 2/9/04Fri 5/7/04
3.3.4.b.3
System No. 3: System Installation/performance verificationFri 4/9/04Fri 8/6/04
3.3.4.b.4
System No. 4: Design/ financing/permittingMon 2/9/04Fri 5/7/04
3.3.4.b.4
System No. 4: System Installation/performance verificationFri 4/9/04Fri 8/6/04
3.3.4.c
PV System Monitoring Mon 1/12/04Fri 10/7/05
3.3.5
Prepare Final Report for Project 3.3Mon 4/11/05Fri 1/6/06
3.3.6
Coordinate with Renewables Project Advisory CommitteeThu 6/20/02Tue 3/7/06
3.3.7.a
Evaluate Project #3.3: Draft Evaluation ReportMon 7/11/05Wed 12/7/05
3.3.7.b
Evaluate Project #3.3: Final Evaluation ReportMon 1/9/06Fri 2/3/06