Project 2.1: Enhanced Landfill Gas Production Using Bioreactors Project
Project Manager - CH2M Hill
Project Overview
Goals and Objectives
The goals of the Enhanced Landfill Gas Production Using
Bioreactors project are to:
- Advance the state of knowledge for using bioreactors at
landfills to increase landfill gas production and
improve the characteristics of the waste to accelerate reclamation
- Work with environmental regulators to develop and implement and strategy for developing
bioreactors while meeting applicable groundwater
and other environmental standards
- Establish the economic and environmental benefits of the use of landfill bioreactors
The objectives of the of this project are to:
- Develop a conceptual design for two types of landfill bioreactors
- MSW or organic waste landfill bioreactor (First Bioreactor)
- MSW or organic waste landfill bioreactor supplemented by food or animal waste (Second
Bioreactor)
- Develop environmental documentation to satisfy regulators
- Quantify greenhouse gas and pollution reduction
benefits
- Develop two types of landfill bioreactors
- MSW or organic waste landfill bioreactor(First Bioreactor)
- MSW or organic waste landfill bioreactor supplemented by food or animal waste (Second
Bioreactor)
Projected Outcomes
The outcome of this project will be the successful operation of two bioreactor pilot
projects. One bioreactor will be designed to use municipal solid waste (MSW) and source-separated
organic waste materials; the other will be designed to use MSW or source-separated organic waste
materials along with animal waste. Performance metrics will include measurement of changes in
methane production; estimation of direct reductions in
CH4 emissions and indirect reductions in other criteria air emissions associated
with displaced conventional generation; and assessment of changes in lifecycle costs of
generation from landfill gas. It is anticipated that the cumulative incremental gas
production from both of these pilot reactors will be in the range of 1 to 5 MW.
In addition to demonstrating the feasibility of developing these bioreactors, two reports will be
developed. One report will summarize the regulatory issues that were addressed and satisfied in the
course of developing this project. This report will include guidelines to be used on future projects
and a methodology for calculating the economic value of environmental benefits of the project. The
second report will summarize the engineering work done to design and install the reactor and present
pertinent installation, operation, and maintenance costs. Project lifecycle costs will be presented
incorporating engineering issues as well as the value of environmental benefits presented in the first
report.
Top
Publications, Reports and Other Deliverables for Project 2.1: Enhanced Landfill Gas Production Using
Bioreactors Project
List of Publications, Reports and Other Deliverables
Project 2.1 Monthly Status Reports
NOTE: All finalized deliverables are available in Adobe Acrobat PDF format. To
obtain a free copy of Adobe® Acrobat® Reader®, please click here.
Task 2.1.1a: Characterize MSW and Source
Separated Organic Waste to Be Placed in Both Bioreactors
Task 2.1.1b: Characterize Food or Animal Wastes
to be Placed as Amendment in the Second Bioreactor
- Landfill Amendment Characterization Report
Task 2.1.2: Identify Amendment Source Locations for the Second
Bioreactor
- Amendment Source Location List
Task 2.1.3a: Prepare Conceptual Design for the First Bioreactor
- Landfill Bioreactor Conceptual Design Report (PDF, 401 KB)
- Figure 2-1 to the Report: Flow Diagram - Energy and Materials Balance (PDF, 401 KB)
- Figure 4-1 to the Report: Process and Instrumentation Diagram (PDF, 66 KB)
- Figure 4-2 to the Report: Instrumentation and Control (PDF, 211 KB)
- Figure 5-1 to the Report: Bottom Grading Plan as Presently Permitted (PDF, 752 KB)
- Figure 5-2 to the Report: Final Grading Plan as Presently Permitted (PDF, 434 KB)
- Figure 5-3 to the Report: North South Cross Section Through Unit 3 (PDF, 221 KB)
- Figure 5-4 to the Report: East West Cross Section Through Unit 3 (PDF, 172 KB)
- Figure 5-5 to the Report: Biocell Phasing Plans Fill Between March 2002 and July 2003 (PDF, 720 KB)
- Figure 5-6 to the Report: Biocell Phasing Plans Fill Between July 2003 and November 2004 (PDF, 707 KB)
- Figure 5-7 to the Report: Biocell Phasing Plans Lift No. 1 to 1,495 Elevation (PDF, 612 KB)
- Figure 5-8 to the Report: Biocell Phasing Plans Lift No. 2 to 1,515 Elevation (PDF, 626 KB)
- Figure 5-9 to the Report: Biocell Phasing Plans Lift No. 3 to 1,535 Elevation (PDF, 140 KB)
- Figure 5-10 to the Report: Biocell Phasing Plans Lift No. 4 to 1,555 Elevation (PDF, 623 KB)
- Figure 5-11 to the Report: Biocell Phasing Plans Lift No. 5 to 1,575 Elevation (PDF, 598 KB)
Task 2.1.3b: Prepare Test and Construction Plans for the First
Bioreactor
Task 2.1.3c: Prepare Conceptual Design for the Second Bioreactor
- Draft Conceptual Design Report for the Second Bioreactor
- Final Conceptual Design Report for the Second Bioreactor
- Groundwater Contamination Risk Report
Task 2.1.3d: Prepare Test and Construction Plans for the Second
Bioreactor
- Second Bioreactor Test Plan
- Final Construction Plan
- Liner Installation Plan
Task 2.1.4a: Construct and Operate the First Bioreactor
- Notification Letter for completion of the Installing Liner
- Notification Letter for completion of the Leachate Collection System
- Notification Letter for completion of the Gas Collection System
- Notification Letter for completion of the Energy Recovery and Prime Mover Systems
- Notification Letter for completion of the Interconnection hardware
- Six Month Operations Report for the First Bioreactor
Task 2.1.4b: Construct and Operate the Second Bioreactor
- Notification Letter for completion of the Installing Liner
- Notification Letter for completion of the Leachate Collection System
- Notification Letter for completion of the Gas Collection System
- Notification Letter for completion of the Energy Recovery and Prime Mover Systems
- Notification Letter for completion of the Interconnection hardware
- Six Month Operations Report for the Second Bioreactor
Task 2.1.5: Prepare Final Report for Project 2.1
- Outline of the Final Report for Project 2.1
- Draft Enhanced Landfill Gas Production Using Bioreactors Report
- Final Enhanced Landfill Gas Production Using Bioreactors Report
Task 2.1.6: Coordinate with Renewables Project Advisory
Committees
Task 2.1.7: Evaluate Project
- Draft Enhanced Landfill Gas Production Using Bioreactors Report
- Final Enhanced Landfill Gas Production Using Bioreactors Report