Project 3.1: Dairy Waste to Energy Project
Project Manager - CH2M Hill
Project Overview
Goals and Objectives
The goals of Dairy Waste to Energy project are to:
- Develop technologies that can be used to maximize the energy recovery from animal waste
- Develop and evaluate different pilot projects that will include facilities at existing treatment plants and at
individual and clusters of dairies
- Evaluate and test the effectiveness of low and high technologies developed in North America and Europe for the
collection processing and energy recovery of animal waste
The objectives of the project are to:
- Assess and evaluate technologies available for the conversion of animal waste to energy including:
- Select Sites for animal waste to energy pilot plant(s)
- Design, construct and operate pilot plant(s)
- Summarize and evaluate economic and environmental costs and benefits associated with developing an
animal waste to energy facilities.
Projected Outcomes
The Dairy Waste to Energy Project will generate the following specific work products: Process flow
diagrams (which integrate the selected process advancements into the selected site) and preliminary facilities
location plans depicting the conceptual layout of the pilot plant, the pilot plant test protocol Plan,
performance specifications, site drawings, and one (or more) operating pilot plant(s) ranging in size from 60 kW
to 5 MWs, with quarterly plant operating reports that document performance and needed modifications throughout the
project.
Top
Publications, Reports and Other Deliverables for Project 3.1: Dairy Waste to Energy Project
List of Publications, Reports and Other Deliverables
Project 3.1 Monthly Status Reports
NIRAS Presentation (Powerpoint, 22 MB)
NOTE: All finalized deliverables are available in Adobe Acrobat PDF format. To
obtain a free copy of Adobe® Acrobat® Reader®, please click here.
Task 3.1.1: Assess, Evaluate, and Select Animal Waste to Energy Technology
Task 3.1.2: Site Selection
Task 3.1.3: Prepare Pilot Plant Final Design and Dairy
Waste to Energy Project Test Plan
- 3.1.3c(1): Pilot Plant(s) Design Memorandum
- 3.1.3c(2): Draft Dairy Waste to Energy Test Plan
- 3.1.3c(3): Final Dairy Waste to Energy Test Plan
Task 3.1.4: Construct Pilot Plant(s)
Task 3.1.5: Operate and Test Pilot Plant(s)
- Draft Monthly Data Report for July, 2005 (PDF, 312 KB)
- Draft Monthly Data Report for August, 2005 (PDF, 311 KB)
- Draft Monthly Data Report for September, 2005 (PDF, 325 KB)
- Draft Monthly Data Report for October, 2005 (PDF, 308 KB)
- Draft Monthly Data Report for November, 2005 (PDF, 309 KB)
- Draft Monthly Data Report for December, 2005 (PDF, 565 KB)
Task 3.1.6: Conduct Economic and Environmental Assessment
Task 3.1.7: Prepare Final Report for
Project 3.1
Task 3.1.8: Coordinate with Renewables Project Advisory Committee
Task 3.1.9: Perform Detailed Distribution Interconnection Study
Task 3.1.10: Dynamic Study of Three BI-PV and Biogas High Penetration Scenarios
Task 3.1.11: Evaluate Project
Top
|