Project 3.3: Building Integrated Photovoltaics on Public Facilities Project
Project Manager - REDI
Goals and Objectives
The goal of Building Integrated PV on Public Facilities project is to demonstrate the potential for taking advantage
of affordability improvements and value added applications by demonstrating a number of new and repeatable project development
approaches in public facilities with relatively large building integrated PV systems. The primary purpose of each of these
pilot demonstrations is to validate ways in which building integrated PV systems can be developed and installed by ESPs,
public entities, or building owners including approaches that can: 1) improve consumer affordability to these higher cost systems,
2) reduce installed PV costs per peak watt (and per life cycle kWh) and, 3) separately, find ways to add outside inherent value to
the PV system installation over its life (i.e., through dual- or tri-use applications of the system).
Projected Outcomes
The Building Integrated PV on Public Facilities Project will yield a set of specific photovoltaic facilities expected to range
in size from 10 kW up to 150 kW, each addressing an infrastructure or commercialization barrier. Thus achieving the PIER objective of
demonstrating the potential for taking advantage of cost economies by installing relatively large PV systems with at least one under
common ownership arrangements. The cumulative capacity of BI-PV systems expected to be procured and installed under this program element
ranges from 120 to 300 kW.
Top
Publications, Reports and Other Deliverables for Project 3.3: Building Integrated Photovoltaics on Public
Facilities Project
List of Publications, Reports and Other Deliverables
Project 3.3 Monthly Status Reports
NOTE: All finalized deliverables are available in Adobe Acrobat PDF format. To
obtain a free copy of Adobe® Acrobat® Reader®, please click here.
Task 3.3.1a: Compile database of Public Sector Clients
- Public-Sector Agencies Database
Task 3.3.1b: Compile Database of BI-PV Equipment Vendors and Service Providers
- Manufacturers and Distributors of BI-PV Equipment Database
Task 3.3.2: Develop Evaluation Tools
- BI-PV Evaluation Tools Package
- Draft BI-PV on Public Facilities Test Plan
- Final BI-PV on Public Facilities Test Plan
Task 3.3.3: Establish BI-PV Public Sector Loan Program
- BI-PV Public Sector Loan Program
Task 3.3.4a: Select Demonstration Project Sites
- Demonstration Site Selection Report
Task 3.3.4b: Finance and Construct BI-PV Systems
- Letters of Notification of receiving finance for each project
- Copy of permit(s)
- Letters of Notification of finishing installation for each BI-PV system/Initial
Performance Results
Task 3.3.4c: System Monitoring
- Semi-Annual Reports of Monitoring Data on all Demonstration Systems
Task 3.3.5: Prepare Final Report for Project 3.3
- Outline of the Final Report for Project 3.3
- Draft Building Integrated PV on Public Facilities Report
- Final Building Integrated PV on Public Facilities Report
Task 3.3.6: Coordinate with Renewables Project Advisory Committee
Task 3.3.7: Evaluate Project
- Draft Building Integrated PV on Public Facilities Project Evaluation Report
- Final Building Integrated PV on Public Facilities Project Evaluation Report